Solving Work And Time Problems How Long Does A Take Alone

by THE IDEN 58 views

In the realm of mathematics, particularly in the domain of work and time problems, scenarios often arise where individuals collaborate to complete a task, and the challenge lies in deciphering the individual contributions and timelines. This article delves into one such intriguing problem, where A and B work together and independently to accomplish a task. We will embark on a step-by-step journey to unravel the intricacies of the problem and arrive at the solution, shedding light on the time taken by A alone to complete the entire work.

Problem Statement

Consider a scenario where A and B work together and complete 8/15th of a task in 5 days. Subsequently, B takes over and completes the remaining portion of the work in 7 days. The crux of the problem lies in determining the time A would take to complete the entire task if working independently. This is a classic work and time problem that tests our understanding of fractions, rates, and collaborative work.

Decoding the Collaborative Work

The initial piece of information states that A and B, working in tandem, manage to complete 8/15th of the work in 5 days. This provides us with a crucial insight into their combined work rate. To quantify this, we can express their combined work rate as the fraction of work completed per day. This initial phase sets the stage for understanding how A and B function as a team, a critical component in solving the overall problem.

Let's dissect this information further. If A and B together complete 8/15 of the work in 5 days, we can find their combined work rate per day. This is a foundational step in understanding their efficiency as a team. To find this rate, we divide the amount of work done (8/15) by the number of days (5). This calculation will give us the fraction of work A and B complete together in one day, setting the stage for further analysis of their individual contributions.

Mathematical Representation

To represent this mathematically, let the total work be 1 unit. The work done by A and B together in 5 days is 8/15. Therefore, their combined work rate per day is:

(8/15) / 5 = 8/75

This means that A and B together complete 8/75 of the work each day. This fraction represents their combined efficiency and is a key element in understanding how they contribute to the completion of the task.

Unveiling B's Individual Contribution

Following their collaborative stint, B takes the reins and completes the remaining portion of the work in 7 days. This piece of information is pivotal in isolating B's individual work rate. By determining how much work B accomplishes in a specific time frame, we gain a clearer understanding of B's efficiency and contribution to the overall task. This step is essential in distinguishing B's capabilities from the combined efforts of A and B, allowing us to eventually deduce A's individual work rate.

The remaining work after A and B's collaboration is the total work minus the work they have already completed. This difference will give us the fraction of work that B completes alone in 7 days. To find B's individual work rate, we will then divide this remaining work by the number of days B worked alone. This calculation will reveal the fraction of work B completes in one day, a critical piece of information for solving the problem.

Calculating the Remaining Work

The total work is considered as 1 unit. A and B completed 8/15 of the work. Therefore, the remaining work is:

1 - 8/15 = 7/15

B completes 7/15 of the work in 7 days. To find B's work rate per day, we divide the work done by the number of days:

(7/15) / 7 = 1/15

Thus, B's work rate is 1/15 of the total work per day. This means B completes 1/15 of the entire task each day when working alone. This individual rate is crucial for disentangling B's contribution from the combined work of A and B, and for ultimately determining how long A would take to complete the work alone.

Isolating A's Work Rate

With the combined work rate of A and B and the individual work rate of B established, we can now isolate A's individual work rate. This step involves a bit of algebraic manipulation, subtracting B's work rate from the combined work rate to reveal A's contribution. By determining A's work rate, we're one step closer to calculating the time A would take to complete the entire task independently. This is a key turning point in the problem-solving process, as it focuses solely on A's efficiency.

To find A's work rate, we subtract B's daily work rate from the combined daily work rate of A and B. This calculation will give us the fraction of work A completes in one day. Understanding A's individual rate is essential for answering the main question of the problem: how long would A take to complete the entire work alone?

Mathematical Deduction

We know that A and B together complete 8/75 of the work per day, and B alone completes 1/15 of the work per day. Therefore, A's work rate per day is:

(8/75) - (1/15)

To subtract these fractions, we need a common denominator, which is 75. So, we rewrite 1/15 as 5/75:

(8/75) - (5/75) = 3/75

Simplifying the fraction, we get:

3/75 = 1/25

Therefore, A's work rate is 1/25 of the total work per day. This means A completes 1/25 of the entire task each day when working alone. With this crucial piece of information, we can now calculate the time it would take A to complete the whole work independently.

Calculating the Time Taken by A Alone

Finally, with A's individual work rate in hand, we can determine the time A would take to complete the entire task independently. This calculation is straightforward, involving dividing the total work by A's work rate per day. This final step provides the answer to the problem, giving us a clear understanding of A's efficiency and the time required to complete the work solo.

The total work is considered as 1 unit, and A completes 1/25 of the work per day. To find the number of days A would take to complete the entire work, we divide the total work by A's daily work rate. This calculation will give us the time in days that A would need to finish the job alone.

The Final Calculation

To find the time taken by A alone to complete the whole work, we divide the total work (1) by A's work rate per day (1/25):

1 / (1/25) = 25 days

Therefore, A alone would take 25 days to complete the entire work. This is the solution to the problem, answering the question of how long A would need to finish the task independently. This result highlights the importance of understanding individual work rates and how they contribute to the overall completion of a project.

Conclusion

Through a meticulous step-by-step analysis, we have successfully determined that A alone would take 25 days to complete the entire work. This problem exemplifies the intricate dance between collaborative and individual efforts in task completion. By dissecting the problem into smaller, manageable steps, we were able to isolate individual work rates and arrive at the solution. The problem underscores the significance of understanding fractions, rates, and collaborative work in the realm of mathematics and real-world applications.

This problem serves as a valuable exercise in understanding how to approach work and time problems, which are common in mathematical problem-solving. By breaking down the problem into smaller parts, we can understand the contributions of each individual and how they work together to complete a task. The solution not only provides the answer to the specific problem but also offers a framework for solving similar challenges in the future. Understanding these concepts is crucial for both academic pursuits and practical applications in various fields.

The ability to dissect complex problems into smaller, manageable components is a valuable skill in mathematics and beyond. This problem, with its collaborative and individual work dynamics, provides an excellent opportunity to hone this skill. The step-by-step approach we've taken, from understanding combined work rates to isolating individual contributions, is a testament to the power of methodical problem-solving. As we navigate similar challenges in the future, the lessons learned from this problem will undoubtedly prove invaluable. This exercise reinforces the importance of critical thinking and analytical skills in mathematics and their applicability to real-world scenarios.